Item Amount Notes
General Conditions
Temporary Facilities & Misc$8,000
Dumpsters / Hauling$30,000See General Notes below
Scaffolding$7,500
General Labor & Supervision$65,000
Permits$0Waived for fire-built projects in California
Final Cleaning$3,500
Registered Deputy Inspection$0Not included — See General Notes
Business License$0
Subtotal — General Conditions$114,000
Construction
Demolition, Recycling, & Disposal$15,000
Rough Grading & Compaction$65,000Includes all compactions
Concrete — Sitework$68,000See General Notes below
Concrete — Building$66,000
Masonry — House$32,500Waterproofing included
Masonry — Site$24,500
Metal Fabrications$11,000
Metal Railings$22,000
Rough Carpentry Material$46,000
Rough Carpentry Labor$54,000
Finish Carpentry Material$42,000
Finish Carpentry Labor$48,000
Cabinetry$52,000
Clay Tile Roofing$21,500
Built-Up Roofing$7,200
Waterproofing$8,750
Deck Coating$9,500
Flashing & Sheet Metal$8,800
Gutters / Downspouts$6,700
Joint Sealants$3,800
Insulation$21,000
Interior Doors & Frames$15,800
Exterior Doors$38,000ALUMIL European Aluminum exterior doors
Door Hardware Allowance$7,400Baldwin Estate cylinder locks, Oil-Rubbed Bronze
Windows$32,000ALUMIL European Aluminum windows
Finish Hardware Allowance$4,200
Mirrors Allowance$2,000
Plaster & Weather Barrier$38,500
Drywall$39,800
Tile Labor$18,500
Tile Materials Allowance$12,000$5.50/sf — Approx. 450 sf flooring + 1,400 sf walls
Stone Counters Allowance$11,500Three slabs for kitchen island and countertops
Hardwood Flooring Allowance$14,000$5.50/sf — Approx. 2,300 sf hardwood flooring
Painting$36,000
Shower Doors / Enclosures$4,600
Plumbing$54,000
Bath Accessories Allowance$2,800Install all Owner-provided bath accessories — towel bars, rings, hooks, TP holders, mirrors
Plumbing Fixtures Allowance$8,000Install Owner-selected plumbing fixtures
HVAC$34,700
Gates$4,200
Fencing$28,000Approx. 160 linear ft, 30" and 42" high metal fence. Includes all block walls
Electrical$42,000
Decorative Lighting & Fans Allowance$7,200Install all surface-mounted and decorative lighting
Low Voltage, incl. Smoke Detectors$10,500
Exterior Landscape Lighting Allowance$2,500
Site Drainage$7,900
Landscape & Irrigation Allowance$30,000Soils amendments, landscape, garden lighting, and irrigation
Utility Connections$2,500Timely connection of water, sewer, gas, power, and telecom
Fire Sprinklers (NFPA 13D)$15,000
BBQ Buildout$10,000
Interior Fireplace$11,800Includes the fireplace and installation
Garage Door$7,500
Subtotal — Construction$1,186,150
Project Contingency 5% $59,308
Overhead Bidder to select Bidder to select
Profit 12% $142,338Bidder to select
Total Cost to Owner$1,501,796
Revised Total Cost $1,500,000
General Notes

Soil Report

The project scope includes excavation to a depth of approximately 4 feet for the foundation, followed by backfill in 8-inch lifts with compaction at each layer. Each lift shall be subject to inspection and approval by the Deputy Inspector prior to proceeding to the next phase of backfill.

In the event the on-site soil does not meet the required compaction standards or is deemed unsuitable by the Deputy Inspector, the existing material will need to be exported (estimated at approximately 750 cubic yards), and approved import material will be required for replacement. This condition would result in an additional cost to the project in the approximate amount of $85,000.

Concrete Site Work

The geotechnical report requires the same excavation, recompaction, and inspection process for the driveway area; accordingly, the driveway shall be constructed under the same procedures outlined above, utilizing approved on-site soil.

Additionally, the 30-inch perimeter wall enclosing the house and driveway, which is impacted by these requirements, is directly affecting the masonry and concrete work.