McMullins Residence
Like-for-Like Eaton Fire Rebuild
Site map
1245 Rubio Vista Rd,
Altadena,
CA 91001

APN #: 5843-029-030

Architect: Tyler + Kelly Architecture, Inc.

Structural Engineer: Hwang Structural Engineers Inc.

Civil Engineer: Tritech Engineering Group

Owner: Tommy McMullins

Project Description

The scope of work consists of reconstructing a two-story single-family residence with an attached two-car garage on the existing lot. The project will comply with all applicable rebuilding provisions, local regulations, and building codes governing fire-affected properties.

The proposed residence is a two-story, 2,528 SF single-family home with a 514 SF attached two-car garage, replacing a previously existing 2,298 SF single-family residence with a 400 SF attached two-car garage. The project also includes new landscaping, hardscaping, and perimeter fencing.

Site plan

Deferred Submittals

Separate permit is required for the following:

1. Fire Sprinklers. Deferred Submittal.
2. Landscaping. Separate Permit.

The architect/engineer of record shall review and approve deferred submittals prior to submittal to building department for review. When appropriate, the individual in responsible charge of the project shall forward the deferred submittal to the building department with a notation that the plans have been reviewed and have been found to be in general conformance to the building design. Deferred items shall not be installed until the building department has approved the submittal package.

Order List

  • Windows & doors, handles & accessories
  • Tiles, countertops, backsplashes, hardwood floors
  • Fixtures, faucets, sinks, shower doors
  • Indoor & outdoor fireplaces
  • Roof tiles
  • Water Heater
  • Appliances
  • Lighting fixtures
  • Exterior and Garage doors
  • Gate & Fence material
  • Accessories
  • HVAC Units

Order Milestones

HVAC System – Expected order date: Sept 20, 2026
Roof Tiles – Expected order date: Dec 21, 2027
Windows & Doors – Expected order date: Aug 10, 2026
Windows & Doors should be delivered during the framing process.
Solar System – Expected order date: Sept 21, 2026
Shower Rough Valve – Expected order date: Oct 15, 2026
Tiles – Expected order date: Apr 15, 2027
Lighting Fixtures: Apr 26, 2027
Fixtures, faucets, sinks – Expected order date: Apr 25, 2027
Water Heater – Expected order date: Nov 15, 2026
Shower Doors – Expected order date: May 15, 2026
Appliances – Expected order date: Apr 22, 2027
Garage Door, Gates & Fences: Mar 15, 2027
Accessories: May 26, 2027

Permit: Submitted
Permit Status: Pending
Site Safety: To be Processed
Site Survey & Staking: To be Processed
Site assessment: To be Processed
Land clearing for excavation & grading: To be Processed
Drainage planning: To be Processed
Pre-inspection: To be Processed

May 29,
2026
Foundation & Rough Utilities
Foundation
  • Excavation & Dirt Removal
  • Installing Forms
  • Adding Structural Rebar
Rough Plumbing
  • Installation
  • Underground Utilities
Inspection (Rebar, Plumbing & Footing)
Foundation Completion
  • Placing the Concrete
  • Stripping the Forms
  • Framing Layout
Final Foundation Inspection
Aug 29,
2026
Framing & Insulation
Framing (Sill plates, joists, subflooring, studs, windows & doors openings, top plates, beams and ceiling joists, rafters)
Rough Electrical & Plumbing (Wiring, Low Voltage, Pipes, Rough Valves, etc.)
Framing & Electric Inspection
HVAC & Solar Panel
Insulation
  • Insulation between the joists and below roof deck
  • Insulation above ceiling between joists
Insulation Inspection
Windows & Doors Installation
Dec 10,
2026
Drywall, Roof & Stucco
Drywall
Roofing
  • Lay underlayment
  • Flashing in valleys and around dormers
  • Roof tile installment
  • Roofing sealant where needed
Stucco
  • Lath (Water Proof)
  • Base Coat
  • Scratch Coat
  • Brown Coat
Drywall, Roofing & Stucco Inspection
Feb 29,
2027
Finishes
Plumbing (Fixtures, faucets, appliances, sink, shower fixtures, water heater, etc.)
  • Shower hot mop
  • Tile Installation
  • Shower door Installation
Electrical (Panel, recessed lights, outlets, switches, sprinklers, etc.)
HVAC Finishes
Kitchen Cabinets
Flooring (tiles & hardwood flooring)
Painting
Stucco Finishes (Cover With the Finish Coat, Dry Cure, Paint)
Final Inspection
June 06,
2027
Project Completion